Gardenia Park residential complex located in phase 3 of Hashtgerd new city

OMIC

Description Gardenia Park residential complex located in phase 3 of Hashtgerd new city

Operation Place Fashand Region, Phase (3), New Hashtgerd City, Neighborhood 8, Plot 262
Running time 48
Project Consultant Engineer Nezamzadeh and colleagues
Employer phone 021-88213436
Year of project start 2023
Land area 10770 m^2
Total infrastructure 45000 m^2
Number of floors
Number of administrative units 0
Number of business units 0
Number of residential units
Useful office infrastructure (for sale)
Useful commercial infrastructure (for sale)
Useful residential infrastructure (for sale)
Project completion date
Number of parking spaces for sale
Total area of license plates purchased within the project area
Project land area after remediation
Total area of residential infrastructure
Total area of commercial infrastructure 0
Total area of office infrastructure 0

Photo Gallery

Last status

1- Signing the phase 1 and 2 design contract with Arman Zeit consulting engineers (Masoud Nizamzadeh and colleagues)
2- Obtaining a map order and filing a case to obtain a building permit in the municipality
3- Signing a partnership agreement with applicants to participate in the project
4- The end of excavation and concrete execution
5- The start of foundation implementation operations